Aand b can do a work in 6 days ,b and c in 8 days ,and a and c in 10 days if all three work together in how many days will the work will be completed

answer
Answers: 1
Get

Other questions on the subject: Math

image
Math, 18.08.2019 13:00, malikfaiz24
If 2a + 3b-x=c wherea = [2 3 4][-3 0 2] b = [3 -4 -5][0 2 1]andc= [5 -1 2][7 0 3]here a b c are 2×3 matricesfind x matrix ​
Answers: 1
image
Math, 19.08.2019 02:00, bhavya1650
How to division for 4 class in long division​
Answers: 2
image
Math, 19.08.2019 09:00, srabani80pal
Find the volume of a cuboid box whose surface area is 486
Answers: 1
image
Math, 19.08.2019 18:00, srabani80pal
81by2-3 5by8 how will come answer 39by8 =4 7by8
Answers: 3
Do you know the correct answer?
Aand b can do a work in 6 days ,b and c in 8 days ,and a and c in 10 days if all three work together...

Questions in other subjects:

Konu
Social Sciences, 29.03.2020 01:10
Konu
English, 29.03.2020 01:10
Total solved problems on the site: 22027966