Ab and c can do a piece of work in 36 54 and 72 days. started together and after 8 days, a left off. after 12 days b also left off. how many days required to finish the entire job

answer
Answers: 1
Get

Other questions on the subject: Math

image
Math, 16.08.2019 19:00, jack626259
If degree of a road curve is defined by assuming the standard length of an arc as 30 meters, the radius of 1° curve is equal
Answers: 2
image
Math, 18.08.2019 12:00, amruthdeep5258
Two circles, each of radius 7 cm,intersect each other. the distancebetween their centres is 772 cm. findthe area common to both the circles.​
Answers: 1
image
Math, 18.08.2019 13:00, jack626259
If 2a + 3b-x=c wherea = [2 3 4][-3 0 2] b = [3 -4 -5][0 2 1]andc= [5 -1 2][7 0 3]here a b c are 2×3 matricesfind x matrix ​
Answers: 3
image
Math, 19.08.2019 10:00, meandart
Abc is an equilateral triangle. o is a midpoint. od, oe, of are altitude are 10,14,6cm. find the area
Answers: 2
Do you know the correct answer?
Ab and c can do a piece of work in 36 54 and 72 days. started together and after 8 days, a left off....

Questions in other subjects:

Konu
Math, 16.01.2021 06:50
Konu
Math, 16.01.2021 06:50
Konu
Biology, 16.01.2021 06:50
Konu
Math, 16.01.2021 06:50
Total solved problems on the site: 22028941